PPR 2008 Guides
8 published articles.
PPR Rule 98 — Joint Venture Provisions Explained
Rule 98 of PPR 2008 allows two or more eligible firms to form a Joint Venture for works contracts. The lead partner must hold at least 51% stake, and a registered JV Agreement with joint and several liability is mandatory before bid submission.
July 1, 2026PPR Rule 96 — Experience Requirements (Works) Explained
PPR Rule 96 sets mandatory experience requirements for key personnel on works contracts. Bidders must nominate qualified Project Managers, Site Engineers, Quality Control Engineers, and technical specialists with verified credentials, educational qualifications, and comparable project experience.
July 1, 2026PPR Rule 95 — Financial Capacity (Works) Explained
PPR Rule 95 sets mandatory financial capacity requirements for works bidders, including turnover multiples, working capital proof, and audited statements. Learn what procuring entities expect.
June 30, 2026PPR Rule 88 — Similar Work Experience (Works Contracts) Explained
Learn how PPR Rule 88 defines similar work experience requirements for construction tenders in Bangladesh. Understand eligibility thresholds, look-back periods, and how joint ventures can pool credentials.
June 30, 2026PPR Rule 27 — Evaluation Criteria Explained
PPR Rule 27 mandates that all evaluation criteria—technical and financial—must be clearly stated in tender documents at issuance and cannot be modified after bid submission. Criteria include pass/fail responsiveness checks and merit-point scoring, with deviations grounds for bid challenge.
June 29, 2026PPR Rule 25 — Bid Validity Period Explained
PPR Rule 25 sets the timeframe during which bidders remain bound to their submitted bids. Learn standard validity periods, extension procedures, and contract award deadlines.
June 29, 2026PPR Rule 23 — Bid Security Explained
PPR Rule 23 requires bid security (earnest money) for procurements above BDT 10 lakh. Learn the forms, amounts, validity periods, and forfeiture conditions that apply to all bidders in Bangladesh public procurement.
June 28, 2026PPR Rule 16 — Procurement Methods Explained
Rule 16 of PPR 2008 defines five principal procurement methods: Open Tendering, Limited Tendering, Direct Procurement, Request for Quotation, and Two-Stage Tendering. Each method serves specific procurement scenarios and must be justified in the procurement plan.
June 28, 2026